1. DEFINITIONS
Construction Quality Control (CQC) is a planned system of routine inspections that is used to directly monitor and control the quality of a construction project.
Construction Quality Assurance (CQA) is independent of the CQC and includes inspections, verifications, audits, and evaluations of materials and workmanship necessary to determine and document the quality of a construction project.
2. PARTIES
This manual references different parties which may be involved in the liner installation process. A successful liner installation depends on the responsible and timely interaction of all involved parties and coordination of all installation, inspection, testing, and documentation.
| Owner |
Owner of the property and/or facility; responsible for the final acceptance
of the work done on his property/facility. |
| |
| Designer |
Architectural and/or engineering entity responsible for project planning,
design, specifications, and drawings. The designer may also be the project manager. |
| |
| Project Manager |
Authorized representative of the owner; in charge of project scheduling and
coordination of construction activities. |
| |
| General Contractor |
Prime contractor for the project; may delegate specific tasks in a
contractual agreement to one or more subcontractors. The general contractor is sometimes the liner system
installer and/or the earthwork contractor. |
| |
| Liner System Installer |
Subcontractor for the complete installation of the synthetic liner system; must perform according to its contract with the owner or the general contractor. |
| |
| Liner Manufacturer |
(Poly-Flex, Inc.) manufacturer of the geomembrane from raw material (resin).
|
| |
| Soil CQA Consultant |
Party, independent of the general contractor and the liner installer, in
charge of monitoring, testing, inspecting, and documenting all earthwork. Also called soil inspector.
|
| |
Geosynthetic CQA Consultant |
Party, independent of the general contractor and the liner installer, who
monitors, tests, inspects, and documents the installation of all geosynthetic materials, i.e. geomembranes,
geotextiles, geonets, and geogrids. Also called third party CQA or liner inspector. |
| |
| Independent Laboratory |
Testing laboratory unaffiliated with the geosynthetic material manufacturer,
installer, or the general contractor for a project. |
|